What is this scheme?
A Central scheme to link villages and hamlets without roads usable in all seasons (including the monsoon) with main roads. A road lets farmers take produce to market easily, students reach school, patients reach hospital and employment opportunities grow.
PMGSY-IV details
- Implemented from 2024-25 to 2028-29 at a total cost of Rs 70,125 crore (Centre Rs 49,087.5 crore, states Rs 21,037.5 crore).
- The aim is roads for 25,000 unconnected habitations and about 62,500 km of all-weather roads, including the required bridges.
- Population limits: habitations with over 500 people in plains, over 250 in hill and North-Eastern states and over 100 in extremism-affected districts (2011 Census).
- Reports say the deadline for completing PMGSY-III works was extended to March 2028 (March 2029 for hill bridges).
- Government information says thousands of km of roads were sanctioned in many states in early 2026.
If you want a road to your village
- Check whether your village meets the population criteria above under the 2011 Census, and whether it already has a road (see “OMMAS” information on pmgsy.nic.in).
- Pass a resolution in the gram sabha and give a request to your elected representative (MLA/MP) through the mandal parishad / zilla parishad.
- Get the request recorded at the rural roads department / Panchayat Raj engineering office.
- The State Rural Roads Development Agency (SRRDA) adds it to the priority list and sends proposals to the Centre.
Quality monitoring and complaints
- Through the Meri Sadak mobile app you can complain with photos about the quality of road works or problems.
- While a road is being built, a board should show the scheme, cost and deadline. If not, you may ask about it.
- Independent monitoring agencies inspect the quality of works.